Capital Street Improvements

The following is a list of capital street improvements in the Town of Grand Bay-Westfield for 2023.

Location: Prosser Court (Entire Section)
Summary of Work: Work consists of road reconstruction, asphalt base repairs, asphalt resurfacing and site restoration.
Capital Investment: $80,000
Approximate Start Date: July 4, 2023
Approximate End Date: August 4, 2023

Location: Lacroix Drive (Route 102 to Windsor Street)
Summary of Work: Work consists of culvert repairs, road reconstruction, asphalt base repairs, asphalt resurfacing and site restoration.
Capital Investment: $295,000
Approximate Start Date: July 4, 2023
Approximate End Date: August 4, 2023

Location: Nerepis Road (Golf Club Road to Hillandale Drive)
Summary of Work: Work consists of the install of new concrete curb & gutter, repair of existing storm sewer, asphalt restoration and landscaping.
Capital Investment: $173,000
Approximate Start Date: Oct. 30, 2023
Approximate End Date: Nov. 10, 2023